Client: Aurora Land Consulting
JPS Division: Pipeline Services
Project Type: Reclamation, Mainline Support
Project Location: Alberta
Time Frame: 3.5 Months
Contract Type: Time + Materials
Scope of Work
Mitigate pipeline construction deficiencies
Reclamation & erosion control
Land clearing & widow strip removal
R.O.W. fencing, landowner fencing, cattle crossings
De-watering & access management
Manage & mitigate landowner deficiencies
Access road construction & repair
Vegetation control & management
Equipment Used on Project
80-200 Series Excavator
70-110 Hp Skid-steers
14M Motor Grader
200 Hp Wheel Loader w/ Matt Grapple
250 Hp Grapple Skidder
300 Hp Mulchers
Personnel Carriers: Argo's, Side by Sides, Quads
Hydro Vac Truck
Tandem Gravel Trucks
Picker Truck, Service Truck, Tractors & Trailers
Water pumps, generators, light plants, washrooms
Challenges Overcome
Worked cohesively with landowners, municipalities and other contractors
Completed projects adjacent to wetlands & other water bodies without negatively impacting the surrounding environment
Met all environmental guidelines set forth by governing bodies such as the AER, AEP and Environment Canada throughout the construction and reclamation process
Completed the project with no major incidents
Managed project schedule to meet all demands of the client, landowners & other contractors while successfully mitigating the spread of clubroot.
Safety Stats
Total Recordable Incidents: 0
LTI/Frequency: 0
TRI/Frequency: 0
Manhours: 27,310