Home NSR Subsurface Drainage System
Client: Top 3 Midstream Companies in Canada
JPS Division: Energy

Project Type: Slope Stabilization & Erosion Control

Project Location: Heartland Industrial Park

Time Frame: September 2022 – October 2022

Contract Type: Gross Maximum, Time & Materials

Scope of Work

R

Steep Slope reclamation

R

Excavate around live 12” HPS

R

Supply and install subsurface drainage system

R

Steep slope stabilization over water body (river)

R

Construct water diversion berms

Equipment Used on Project

R

80, 210, 350 & 470 series excavators w/ tilt buckets & hoe-pacs

R

D5 K2 CAT, (x2) D7 Winch CAT

R

250 Hp wheel loaders

R

Terramac T-14 (Morooka)

R

100 Hp skid steers x2

R

Personnel carriers: UTV’s

R

Laydown equipment: office trailer, wash car, etc.

Challenges Overcome

R

Working with heavy equipment on the river’s edge, within the 5 year water mark, no spills or regulation violations.

R

Successful reclamation & stabilization of 53% slope on right-of-way.

R

Safety utilized excavators tied off to winch CAT’s to execute the work with zero incidents