Home Costco

Client: Costco Wholesale

JPS Division: Civil Construction Services

Project Type: Excavation, Base Stabilization, Asphalt Paving, Concrete

Project Location: Edmonton, Alberta

Time Frame: July 2019 – September 2019

Contract Type: Lump Sum Bid

Scope of Work

R

Mitigate sinkholes forming in parking lot and concrete structures around building

R

Investigate root cause & eliminate source of underground seepage

R

Supply & implement traffic management plan for both foot & vehicle traffic

R

Excavate & dispose of damaged concrete & asphalt

R

Excavate & dispose of saturated base materials

R

Replace damaged manhole barrels & catch basins

R

Supply & compact 20mm & 40mm aggregates

R

Stabilize base using soil cement as required

R

Supply & install geo-grid and geo-textile

R

Mill 100mm asphalt repair overlap

R

Pave 250mm HD Asphalt with CAT AP1055 Highway Paver

R

Supply & install 15m & 20m rebar

R

Place & finish 200mm of 32mpa concrete

Equipment Used on Project

R

80 & 250 Series Excavators

R

20 Ton Gradall

R

100 Hp Skid-steer

R

Fleet of Tandem Gravel Trucks

R

RC & Enclosed Cab Compactors

R

CAT AP1055D Asphalt Paver

R

Wirtgen W120F Asphalt Cold Milling Machine

Challenges Overcome

R

Worked together with Costco staff and the City of Edmonton to complete the project without negatively affecting the operation of the store or the surrounding community

R

Completed project without any safety incidents

R

24 hour access maintained for fuel trucks, shipping/receiving truck traffic, Costco personnel & patrons

R

98% compaction gained on base repairing sinkhole

Safety Stats

Total Recordable Incidents: 0

LTI/Frequency: 0

TRI/Frequency: 0

Manhours: 3,240