Home NSR Emergency Slope Stabilization
Client: Top 3 Midstream Companies in Canada
JPS Division: Energy

Project Type: Slope Stabilization & Erosion Control

Project Location: Heartland Industrial Park

Time Frame: January 2022 – June 2022

Contract Type: Gross Maximum, Time & Materials

Scope of Work

R

Construct roadways & pads

R

Place & compact aggregates

R

Install erosion control measures in frozen conditions

R

Install precast concrete anchor blocks

R

Steep slope stabilization over water body (river)

R

Directional drilling support

R

Material supply & logistics (40,000 tonne)

Equipment Used on Project

R

210, 350, 470 & 550 series excavators

R

170 - 250 Hp wheel loaders

R

(x2) Morooka’s, (x2) 30 tonne rock trucks

R

100 Hp skidsteer

R

Personnel carriers: UTV’s

R

Laydown equipment: office trailer, wash car, etc.

Challenges Overcome

R

Working with heavy equipment on the river’s edge, within the 5 year water mark, no spills or regulation violations.

R

Successfully installed ESC materials & base in frozen ground conditions

R

Efficiently worked with several sub trades on-site